After more than two decades of planning, Easton Airport is moving ahead with construction of a new runway following two major approvals by the Talbot County Council at its October 27 meeting.
The council unanimously approved an $8.46 million construction change order for David A. Bramble Inc. and a separate $433,120 agreement with AECOM for construction management. Airport Manager Micah Risher told council members that federal and state aviation grants had been secured and that construction could begin October 29.
The project represents a major milestone in an effort that began in the early 2000s, when updated Federal Aviation Administration safety requirements created the need to reconfigure Easton’s primary runway. An environmental assessment began in 2006, and the modernization plan received approval in 2018.
The changes are designed to bring the airport into compliance with federal runway safety standards while improving its existing facilities. The completed primary runway will measure 6,400 feet, with the project shifting the runway configuration to provide adequate safety areas.
Risher outlined a construction schedule beginning with grading and soil preparation near the former Black & Decker property. Crews will prepare the new runway area before winter, with paving expected in March and April 2027. Approximately 2,700 feet of new pavement will be constructed during this phase.
Although much of that work should be completed by summer 2027, additional improvements, including lighting, pavement markings, connecting taxiways and removal of a portion of the existing runway, will be necessary before the new configuration becomes operational.
Risher estimated that the new runway could open within 12 to 18 months, with the longer timeframe considered more likely.
The work will also affect airport operations. Easton Airport has announced significant closures of Runway 4/22 beginning October 29, with temporary openings planned around the Waterfowl Festival and Thanksgiving. The airport’s secondary runway, 15/33, will remain available for normal operations.
Risher said the airport had budgeted $1.45 million toward the project but expects its actual contribution to be approximately $970,000, with federal and state grants providing the remaining construction funding.
Council Approves Tourism and Economic Development Merger
In another significant action, the council unanimously approved legislation combining the county’s Economic Development Commission and Board of Tourism into a single advisory board, effective March 1, 2027.
Supporters said the merger would eliminate administrative duplication and allow the county’s economic development staff to devote more time to business retention, expansion and recruitment.
Councilwoman Keasha Haythe noted that the county combined its economic development and tourism departments approximately a decade ago but maintained separate advisory boards. She argued that bringing the boards together was overdue.
Council Vice President Pete Lesher questioned the timing, noting that some existing board members had expressed concerns and suggesting that the incoming council should have an opportunity to consider the legislation.
Lesher voted against advancing the legislation to its final reading but supported the bill itself.
“What I didn’t support was rushing the process,” he explained after the vote.
New Economic Development and Tourism Director Stephanie Mervine, participating remotely, supported the consolidation and said she had been consulting with existing board members about representation of the county’s business sectors.
Hospital and Park Projects Advance
The council also unanimously approved three property transfers supporting two major development projects.
Two resolutions authorize the transfer of county-owned land for infrastructure associated with the new regional medical center in Easton. The property will accommodate roadway access from Route 50 and facilities including a water storage tank and pumping infrastructure.
A third resolution authorizes transferring approximately 1.785 acres of county-owned land to the Town of Easton to provide access to the proposed Woodland Park from the Easton Bypass and Tristan Drive.
Council members described the park agreement as an important step toward creating a new public recreational resource. No members of the public spoke during the hearings on the three resolutions.
The council also approved increased lifetime monthly benefits for qualifying volunteer emergency services personnel and rejected eight bids for improvements to the Hog Neck Golf Course driving range after the proposals exceeded available funding.
The meeting’s most substantial development, however, was the airport construction approval, moving one of Talbot County’s longest-running infrastructure projects into a new phase after years of planning, permitting and preparation.